State of Michigan – Department of Natural Resources – Harvey, MI
Chocolay Trail Bridge M-28 Repairs
Scope of work included: Traffic Control, Lead Paint Abatement, Sandblasting existing steel, Removal of rotten wood timbers and rubber belting, Removal of spalled concrete at abutments, Rebuild concrete abutments, Paint existing bridge, installation of new wood timbers, Installation of reclaimed rubber belting, and re-grading of bike path. Project had a three month time limit with liquidated damages. Project was completed in less than two months.