U.S. Army Corps of Engineers – Dead River Basin – Marquette, MI
Dead River Flood Clean Up
Removal and disposal of timber piling field crossing the Dead River. Removal and chipping of woody debris deposited by 2003 flood event.
Phase I: Installation of 300’ of turbidity Curtain & Floating Containment Boom; Removal and disposal of 350 timber pilings Removal and disposal of 72 tons of woody debris
Phase II: Removal and chipping of 16,400 cubic yards of woody debris
Phase III: Removal and chipping of 28,104 cubic yards of woody debris
Phase IV: Removal and chipping of 19,979 cubic yards of woody debris
Phase V: Removal and chipping of 36,176 cubic yards of woody debris